Front Door Framing Arrived Today....

We are ready to close up the house this week to prepare for sheet rock and finish work to begin....up until this point, locking up at night consisted of setting up a piece of plywood across the front entry.  It will be great to get the front door framed so that we can really close up the house.  We are excited about how the front door framing turned out....the white door is a 'dunnage' door - the actual door will be installed just before we move in.




Monday, August 5, 2013

Windows & Garage Slab....

It has been a couple weeks since I have posted since most of the progress has been inside the house.  The rough in plumbing is complete and the HVAC is mostly installed.  We have completed the electrical walkthrough as well as siding.  The next month will be busy.

Here are some pictures with the new windows in....also poured the garage slab today.....